Week 2
Report date - 19th January 2009
Completed brickwork to foundations up to DPC (damp proof course).
Installed internal drainage outlets.
Ground floor installed by Tarmac.
Project team on site
Staff and labour on site consist of:
Building Manager 1
Groundworkers 2
Groundworker Bricklayers 3
Tarmac flooring installers 4
Crane 1
Products and Services installed this week
Tarmac Heatsave Plus
Photos from Week 2 of Build
See photos of the site.