Week 13


3 April 2009

Progress


Roof trusses have been installed and gable brickwork completed.

A decision is required on monitoring equipment urgently as internal works will commence at the latest during w/c 13 April 2009.

During week 14 fascia and soffits will be installed.  Roof tilers have been booked to lathe and felt roof and tile areas where possible, and solar panels will be fitted.



 

Project team on site

Andy Berwick - Lovell - Build Manager
Forklift Driver - 1 (shared with another nearby Lovell scheme)
Scaffolders - 2
Joiners – 2
Apprentice Joiner - 1
Bricklayers - 2

Products and Services installed this week

Roof trusses 
Roof tiling

Photos


See all the photos from the Build


back to top

Tarmac poll

How many different types of concrete do Tarmac offer?


Question mark

Did you know?

Fact 2

Research by Currie and Brown on commercial buildings show that, over a 30-year period, concrete structures are more efficient than steel because they require less energy to heat and cool.  For more benefits see Why Masonry?